Phúc Hưng Cung Ứng Cát Cho Tổ Hợp Thép VinMetal Hà TĩnhPhuc Hung Supplies Sand for VinMetal Ha Tinh Steel ComplexPhúc Hưng为VinMetal河静钢铁联合体供应砂料Phúc Hưng, VinMetal 하띤 제철 단지에 모래 공급Phúc Hưng、VinMetalハティン製鉄コンプレックスに砂を供給
Phúc Hưng cung ứng cát xây dựng, cát san lấp cho Tổ hợp thép VinMetal Hà Tĩnh, dự án thép gần 80.000 tỷ đồng của Vingroup tại Vũng Áng.Phuc Hung supplies construction and fill sand for VinMetal Ha Tinh, Vingroup’s nearly VND 80 trillion steel complex in Vung Ang.Phúc Hưng为VinMetal河静供应建筑用砂和回填砂。该项目是Vingroup在永安投资近80万亿越南盾的钢铁联合体。Phúc Hưng은 Vingroup이 붕앙에 건설 중인 약 80조 VND 규모의 제철 단지 VinMetal 하띤에 건설용 모래와 매립용 모래를 공급합니다.Phúc Hưngは、ブンアンに建設中のVingroupによる総額約80兆VNDの製鉄コンプレックス、VinMetalハティンに建設用砂と埋立用砂を供給しています。
Phúc Hưng Cung Ứng Cát Cho Một Trong Những Tổ Hợp Thép Quy Mô Lớn Nhất Việt Nam
Tại Khu kinh tế Vũng Áng, tỉnh Hà Tĩnh, một tổ hợp công nghiệp nặng quy mô hàng chục nghìn tỷ đồng đang được triển khai. Trong chuỗi cung ứng cho dự án, Phúc Hưng đảm nhận việc cung cấp cát xây dựng và cát san lấp cho các hạng mục hạ tầng của Nhà máy sản xuất thép VinMetal Hà Tĩnh, dự án thuộc hệ sinh thái Vingroup.
Quy mô đầu tư vượt trội
VinMetal Hà Tĩnh có tổng vốn đầu tư gần 79.986,5 tỷ đồng, sử dụng khoảng 461 ha đất tại Khu công nghiệp Vinhomes Vũng Áng, theo giấy chứng nhận đăng ký đầu tư cấp tháng 2/2026. Riêng về diện tích mặt bằng, dự án vượt qua cả tổ hợp thép Hòa Phát Dung Quất 2 — một trong những dự án thép lớn nhất Việt Nam hiện nay với khoảng 280 ha và vốn đầu tư khoảng 85.000 tỷ đồng — với quy mô tương đương gấp 1,6 lần. Đến tháng 7/2026, quy hoạch chi tiết tỷ lệ 1/500 tiếp tục được phê duyệt với diện tích 459,68 ha, trong đó đất dành cho công trình sản xuất và kho tàng chiếm hơn 2,63 triệu m², phần còn lại hơn 1,31 triệu m² dành cho cây xanh và mặt nước cảnh quan. Với quy mô mặt bằng lớn như vậy, khối lượng cát san lấp cần huy động để hoàn thiện nền đất trước khi xây dựng là rất đáng kể — đây chính là phần việc Phúc Hưng đang cung ứng cho dự án. Khi hoàn thành, dự án dự kiến tạo việc làm cho hơn 5.000 lao động.
Sản xuất thép chất lượng cao cho xe điện và hạ tầng tốc độ cao
Dự án được định hướng sản xuất các dòng thép tấm cán nóng (HRC), thép cán nóng, thép cường độ cao và thép hợp kim đặc chủng, nhắm tới các lĩnh vực đòi hỏi tiêu chuẩn kỹ thuật khắt khe như sản xuất ô tô điện, công nghiệp chế tạo và hạ tầng giao thông tốc độ cao, bên cạnh dòng thép dân dụng phục vụ xây dựng.
Hợp tác công nghệ với Primetals Technologies
VinMetal lựa chọn Primetals Technologies làm đối tác tích hợp công nghệ cho toàn bộ chuỗi sản xuất, từ luyện gang, luyện thép đến cán thép thành phẩm, hướng tới sản xuất đồng thời cả thép dài và thép dẹt theo công nghệ xanh, số hóa và các tiêu chuẩn quốc tế. Hợp đồng cung cấp toàn bộ công nghệ luyện thép, đúc liên tục và cán thép đã được ký kết vào cuối tháng 6/2026, với hệ thống dự kiến gồm lò chuyển BOF 200 tấn, dây chuyền đúc phôi, cán thép dây, cán thép thanh tốc độ cao và cán nóng HRC.
Tiến độ triển khai và cam kết môi trường
VinMetal đặt mục tiêu cho ra mẻ thép đầu tiên vào đầu năm 2027, và từ tháng 9/2026 đã bắt đầu tuyển dụng đội ngũ nhân sự cho nhà máy cán thép xây dựng tại Vũng Áng, bao gồm các vị trí quản lý, tổ trưởng, kỹ sư, kỹ thuật viên và nhân sự kiểm soát chất lượng. Để công trường kịp mục tiêu ra mẻ thép đầu tiên theo đúng kế hoạch, nguồn cát phục vụ san nền và thi công hạ tầng cũng phải được Phúc Hưng vận chuyển tới tận chân công trình với khối lượng lớn và đúng tiến độ khẩn trương này. Về môi trường, dự án áp dụng mô hình Zero Liquid Discharge để thu hồi, tái sử dụng gần như toàn bộ nước công nghiệp, đồng thời thu hồi khí phát sinh từ quá trình luyện kim để phát điện, gia nhiệt và tái sử dụng trong nhà máy, hướng tới đáp ứng các tiêu chuẩn BAT của châu Âu.
Tiếp nối kinh nghiệm cung ứng vật liệu cho các dự án trọng điểm khác của Vingroup như Khu đô thị Thể thao Quốc tế Hà Nội và VinFast Vũng Áng, Phúc Hưng xem việc đồng hành cùng VinMetal Hà Tĩnh là một dấu mốc đáng chú ý, góp phần vào một trong những dự án công nghiệp nặng quan trọng nhất của hệ sinh thái Vingroup tại khu vực miền Trung.
Phuc Hung Supplies Sand for One of Vietnam’s Largest Steel Complexes
In the Vung Ang Economic Zone, Ha Tinh Province, a heavy-industry complex worth tens of trillions of Vietnamese dong is taking shape. Within the project’s supply chain, Phuc Hung is responsible for supplying construction and fill sand for the infrastructure works at the VinMetal Ha Tinh steel plant, a project within the Vingroup ecosystem.
An Investment of Exceptional Scale
VinMetal Ha Tinh carries a total investment of approximately VND 79,986.5 billion and occupies roughly 461 hectares within the Vinhomes Vung Ang Industrial Park, according to the investment registration certificate issued in February 2026. In terms of land area alone, the project surpasses the Hoa Phat Dung Quat 2 steel complex — one of Vietnam’s largest steel projects, spanning approximately 280 hectares with an investment of around VND 85 trillion — by roughly 1.6 times. By July 2026, the 1/500-scale detailed master plan was approved for an area of 459.68 hectares, of which more than 2.63 million square meters is allocated to production facilities and warehousing, and a further 1.31 million square meters to green space and water landscaping. A site of this scale requires substantial volumes of fill sand to prepare the ground before construction can begin — the exact role Phuc Hung is fulfilling on this project. Once operational, the project is expected to create jobs for more than 5,000 workers.
High-Grade Steel for Electric Vehicles and High-Speed Infrastructure
The plant is designed to produce hot-rolled coil (HRC) steel sheet, hot-rolled steel, high-strength steel, and specialty alloy steel grades, targeting sectors with demanding technical requirements such as electric vehicle manufacturing, industrial fabrication, and high-speed transport infrastructure, alongside civil construction-grade steel.
A Technology Partnership with Primetals Technologies
VinMetal has selected Primetals Technologies as its technology integration partner across the entire production chain, from ironmaking and steelmaking through to finished rolled steel, with plans to produce both long and flat steel products using green, digitalized technology aligned with international standards. The contract covering the full steelmaking, continuous casting, and rolling technology package was signed in late June 2026, with the system expected to include 200-ton BOF converters, billet casting lines, wire rod rolling, high-speed bar rolling, and HRC hot-rolling lines.
Implementation Progress and Environmental Commitments
VinMetal is targeting its first steel output in early 2027, and began recruiting staff for the construction-steel rolling mill at Vung Ang in September 2026, covering management, team leader, engineering, technical, and quality control positions. To help the site stay on track for that first-output target, the sand needed for grading and infrastructure work is delivered by Phuc Hung directly to the job site in large volumes, matched to this demanding schedule. On the environmental side, the project applies a Zero Liquid Discharge model to recover and reuse nearly all industrial water, while gas generated from the metallurgical process is recovered for power generation, heating, and reuse within the plant, in line with European BAT standards.
Building on experience gained supplying materials to other flagship Vingroup projects, including the Hanoi International Sports City and VinFast Vung Ang, Phuc Hung regards its involvement in VinMetal Ha Tinh as a notable milestone, contributing to one of the most significant heavy-industry projects within the Vingroup ecosystem in Vietnam’s central region.
Phúc Hưng为越南最大钢铁联合体之一供应砂料
在河静省永安经济区,一座投资数十万亿越南盾的重工业联合体正在成形。在该项目供应链中,Phúc Hưng负责为VinMetal河静钢厂的基础设施工程供应建筑用砂和回填砂,该项目隶属Vingroup生态系统。
规模非凡的投资
根据2026年2月颁发的投资登记证,VinMetal河静总投资约799,865亿越南盾,占地约461公顷,位于Vinhomes永安工业园区内。仅就占地面积而言,该项目约为Hoa Phat Dung Quat 2钢铁联合体的1.6倍——后者是越南最大的钢铁项目之一,占地约280公顷,投资约85万亿越南盾。截至2026年7月,1/500比例详细规划获批,面积为459.68公顷,其中超过263万平方米用于生产设施和仓储,另有131万平方米用于绿化和水景。如此规模的场地在开工前需要大量回填砂进行场地平整——这正是Phúc Hưng在该项目中承担的角色。项目建成投产后,预计将为5,000多名工人创造就业岗位。
服务电动汽车与高速基础设施的高等级钢材
该钢厂设计生产热轧卷板(HRC)、热轧钢、高强度钢及特种合金钢,面向电动汽车制造、工业制造和高速交通基础设施等技术要求严苛的领域,同时也生产民用建筑钢材。
与Primetals Technologies的技术合作
VinMetal选定Primetals Technologies作为其全生产链的技术集成合作伙伴,涵盖从炼铁、炼钢到成品轧材的全过程,计划采用符合国际标准的绿色、数字化技术生产长材和板材。涵盖炼钢、连铸和轧制全套技术的合同已于2026年6月下旬签署,系统预计包括200吨BOF转炉、方坯连铸线、线材轧制线、高速棒材轧制线以及HRC热轧线。
实施进度与环保承诺
VinMetal目标于2027年初产出第一炉钢,并于2026年9月开始为永安建筑钢轧钢厂招聘员工,涵盖管理、班组长、工程、技术和质量控制等岗位。为确保工地按期实现首批出钢目标,平整场地和基础设施工程所需的砂料由Phúc Hưng大批量直接运送至工地,以配合这一紧张的工期。在环保方面,项目采用零液体排放(Zero Liquid Discharge)模式,回收并重复利用几乎全部工业用水;冶金过程产生的煤气则被回收用于发电、供热及厂内再利用,符合欧洲BAT标准。
凭借此前为Vingroup其他旗舰项目(包括河内国际体育城和VinFast永安)供应材料所积累的经验,Phúc Hưng将参与VinMetal河静项目视为一个重要里程碑,为Vingroup生态系统在越南中部地区最重要的重工业项目之一贡献力量。
Phúc Hưng, 베트남 최대 규모 제철 단지 중 한 곳에 모래 공급
하띤성 붕앙 경제특구에서 수십조 VND 규모의 중공업 단지가 모습을 갖춰 가고 있습니다. 이 프로젝트의 공급망에서 Phúc Hưng은 Vingroup 생태계에 속한 프로젝트인 VinMetal 하띤 제철소 인프라 공사에 건설용 모래와 매립용 모래를 공급하는 역할을 맡고 있습니다.
이례적인 규모의 투자
2026년 2월 발급된 투자등록증명서에 따르면, VinMetal 하띤의 총투자액은 약 79조 9,865억 VND이며, Vinhomes 붕앙 산업단지 내 약 461헥타르 부지를 차지합니다. 부지 면적만 보더라도 이 프로젝트는 베트남 최대 제철 프로젝트 중 하나로 약 280헥타르 면적에 약 85조 VND가 투자된 Hoa Phat 중꾸앗 2 제철 단지보다 약 1.6배 큽니다. 2026년 7월에는 459.68헥타르 면적에 대한 1/500 축척 상세 마스터플랜이 승인되었으며, 이 중 263만㎡ 이상이 생산 시설 및 창고에, 131만㎡가 녹지 및 수경 공간에 배정되었습니다. 이처럼 대규모 부지는 착공 전 지반 조성을 위해 막대한 양의 매립용 모래가 필요하며, 바로 이것이 이 프로젝트에서 Phúc Hưng이 수행하는 역할입니다. 가동 후에는 5,000명 이상의 일자리를 창출할 것으로 기대됩니다.
전기차 및 고속 인프라를 위한 고급 강재
이 공장은 열연 코일(HRC) 강판, 열연 강재, 고강도강 및 특수 합금강을 생산하도록 설계되었으며, 일반 건설용 강재와 함께 전기차 제조, 산업용 가공, 고속 교통 인프라 등 기술 요구 수준이 높은 분야를 목표로 합니다.
Primetals Technologies와의 기술 파트너십
VinMetal은 제선, 제강부터 압연 완제품에 이르는 전체 생산 체인의 기술 통합 파트너로 Primetals Technologies를 선정했으며, 국제 표준에 부합하는 친환경·디지털 기술로 봉형강과 판재 제품을 모두 생산할 계획입니다. 제강, 연속 주조 및 압연 기술 패키지 전체에 대한 계약은 2026년 6월 말에 체결되었으며, 이 시스템에는 200톤급 BOF 전로, 빌릿 연주 라인, 선재 압연, 고속 봉강 압연 및 HRC 열간 압연 라인이 포함될 예정입니다.
추진 현황 및 환경 약속
VinMetal은 2027년 초 첫 쇳물 생산을 목표로 하고 있으며, 2026년 9월부터 붕앙 건설용 강재 압연 공장의 관리직, 조장, 엔지니어, 기술직 및 품질 관리직 인력 채용을 시작했습니다. 현장이 첫 생산 목표를 차질 없이 달성할 수 있도록, 정지 및 인프라 공사에 필요한 모래를 Phúc Hưng이 빠듯한 일정에 맞춰 대량으로 현장에 직접 납품하고 있습니다. 환경 측면에서 이 프로젝트는 무방류(Zero Liquid Discharge) 모델을 적용하여 산업용수를 거의 전량 회수·재사용하며, 야금 공정에서 발생하는 가스는 회수하여 발전, 난방 및 공장 내 재활용에 활용하는 등 유럽 BAT 기준을 따릅니다.
하노이 국제 스포츠 시티, VinFast 붕앙 등 Vingroup의 다른 주요 프로젝트에 자재를 공급하며 쌓은 경험을 바탕으로, Phúc Hưng은 VinMetal 하띤 참여를 베트남 중부 지역 Vingroup 생태계에서 가장 중요한 중공업 프로젝트 중 하나에 기여하는 의미 있는 이정표로 여기고 있습니다.
Phúc Hưng、ベトナム最大級の製鉄コンプレックスに砂を供給
ハティン省ブンアン経済区では、数十兆ベトナムドン規模の重工業コンプレックスが形を成しつつあります。このプロジェクトのサプライチェーンにおいて、Phúc Hưngは、Vingroupエコシステムの一員であるVinMetalハティン製鉄所のインフラ工事向けに、建設用砂と埋立用砂の供給を担っています。
類を見ない規模の投資
2026年2月に交付された投資登録証明書によると、VinMetalハティンの総投資額は約79兆9,865億VNDで、Vinhomesブンアン工業団地内の約461ヘクタールを占めています。敷地面積だけで見ても、本プロジェクトはベトナム最大級の製鉄プロジェクトの一つであるホアファット・ズンクアット2製鉄コンプレックス(約280ヘクタール、投資額約85兆VND)の約1.6倍に相当します。2026年7月までに、459.68ヘクタールを対象とする縮尺1/500の詳細計画が承認され、そのうち263万平方メートル以上が生産施設と倉庫に、さらに131万平方メートルが緑地と水景に割り当てられています。これほどの規模の敷地では、着工前の地盤造成に大量の埋立用砂が必要となり、まさにその役割をPhúc Hưngが本プロジェクトで担っています。稼働後は、5,000人以上の雇用創出が見込まれています。
電気自動車と高速インフラ向けの高品位鋼材
同工場は、熱延コイル(HRC)鋼板、熱延鋼材、高張力鋼、特殊合金鋼を生産するよう設計されており、建設用鋼材に加えて、電気自動車製造、産業用加工、高速交通インフラなど、高度な技術要件が求められる分野を対象としています。
Primetals Technologiesとの技術提携
VinMetalは、製銑・製鋼から最終圧延製品に至る全生産工程の技術統合パートナーとしてPrimetals Technologiesを選定し、国際基準に沿ったグリーンかつデジタル化された技術で条鋼と鋼板の両方を生産する計画です。製鋼、連続鋳造、圧延の技術パッケージ全体を対象とする契約は2026年6月下旬に締結され、システムには200トンのBOF転炉、ビレット鋳造ライン、線材圧延、高速棒鋼圧延、HRC熱間圧延ラインが含まれる見込みです。
実施状況と環境への取り組み
VinMetalは2027年初頭の初出鋼を目指しており、2026年9月にはブンアンの建設用鋼材圧延工場の人員募集を開始し、管理職、班長、エンジニア、技術者、品質管理の各職種を募集しています。初出鋼の目標に向けて工程を予定どおり進められるよう、造成工事とインフラ工事に必要な砂は、この厳しいスケジュールに合わせてPhúc Hưngが大量に現場へ直接納入しています。環境面では、本プロジェクトはゼロ液体排出(ZLD)モデルを採用して工業用水のほぼすべてを回収・再利用するとともに、冶金工程で発生するガスを回収して発電、加熱、工場内での再利用に�
てており、欧州のBAT基準に準拠しています。
ハノイ国際スポーツシティやVinFastブンアンなど、Vingroupの他の主要プロジェクトへの資材供給で培った経験を活かし、Phúc Hưngは、ベトナム中部におけるVingroupエコシステムの中でも最も重要な重工業プロジェクトの一つに貢献するVinMetalハティンへの参画を、注目すべきマイルストーンと位置付けています。